PROJECT BREAKDOWN
STOCKTON GROUP delivered the full civils package on behalf of Lindum, supporting the creation of new hospitality facilities and associated infrastructure at one of the UK’s leading race venues.
The works provided the structural foundations, drainage network and external environment needed to bring the redevelopment to life while ensuring the racecourse remained operational and ready for the 2024 season.
DRAINAGE AND SERVICE INFRASTRUCTURE
The works included reduce level excavation and installation of attenuation and storage tanks, alongside internal and external drainage connections across the development footprint.
A coordinated service ducting network was installed, complete with chambers for asset providers, ensuring utilities could be integrated efficiently within the wider redevelopment.
Groundwater ingress during excavation created programme and safety pressures., These were managed through adaptive working methods and close collaboration with the principal contractor, allowing progress to continue while maintaining site standards
REINFORCED CONCRETE AND FOUNDATION WORKS
Substructure works were delivered for the Roberto Bar, Theakston Bar extension, and external canopy structures, including installation of reinforced concrete foundations and floor slabs.
Careful sequencing was essential due to overlapping trades and programme pressures. Through forward planning and flexible construction approaches, the works were completed to specification and aligned with the fixed completion date for the 2024 race season.
HEALTH, SAFETY, AND ENVIRONMENTAL COMPLIANCE
High levels of site activity and constrained working areas required strict adherence to HSEQ procedures throughout the project. Stockton worked closely with Lindum to manage site safety, maintain clear communication, and ensure compliance at every stage.
Despite the technical complexity and scheduling pressures, the project was delivered safely and to the required quality standards.