PROJECT BREAKDOWN
To facilitate delivery of the new driving test centre, Kier Construction appointed STOCKTON GROUP to undertake the civil engineering package, ensuring critical infrastructure and substructure elements were delivered safely and in line with programme requirements.
DRAINAGE DELIVERY
The works included the installation of all underground services plus internal and external drainage systems across the site. This included the installation of soakaway tanks, which are designed to prevent flooding.
During the programme roll-out, several design changes were introduced mid-project. The team adapted sequencing and installation methodologies accordingly, ensuring continuity of works while maintaining compliance with revised specifications and programme requirements.
REINFORCED CONCRETE AND SUBSTRUCTURE WORKS
Foundation works comprised of the construction of building foundations, including excavation, preparation, installation of formwork, reinforcement placement, and the casting of the main concrete floor slab. The slab was delivered to specification, providing the structural base for the new facility.
Careful sequencing and close coordination with other trades were essential, particularly as Stockton joined the project at a later stage and navigated ongoing design adjustments. Despite these challenges, the works progressed efficiently and were completed in line with the planned schedule.
HEALTH, SAFETY, AND ENVIRONMENTAL COMPLIANCE
Challenging ground level constraints and groundwater ingress across various areas of the site required close collaboration between Stockton and Kier Construction to maintain safe working practices throughout.
Stockton’s HSEQ procedures were implemented across the project, ensuring works were delivered safely and to the highest standard while staying on schedule.