Constructing supporting infrastructure for a new AMFresh production line

Author
Gerry Carolan, Operations Director, Civil Engineering
24 August 2026

AM Fresh, a global agrifood and biotechnology group that manages the entire fresh food value chain, needed a new production line to meet an increased demand for orange juice.

Stockton Group was appointed by construction company Lindum to construct the supporting infrastructure for the new production line at its Skelmersdale facility, including drainage and structural and external works as part of a building extension.

 

Decor Constructing supporting infrastructure for a new AMFresh production line
Scope of work

Scope of work

Stockton Group’s role spanned multiple civil engineering disciplines, including the installation of an internal and external drainage system with a pumping functionality, alongside structural reinforcement works for the building extension plus external footpath construction.

Project Summary

Extensive drainage installation
Structural and external works carried out
Project completed on schedule to a high standard

Project Breakdown

Full management

On behalf of Lindum, Stockton project-managed all works from start to finish

100% compliance score

Stockton completed an external Achilles Audit whilst on site, with Stockton earning the maximum score for health, safety, and environmental compliance

Wide range of works

Stockton completed extensive drainage, structural works, and external pathway works 

Quote Author

“Not only did the team deliver multiple works on schedule and to a high standard, but we also received a 100% score from an external auditor, showing out continued commitment to health, safety, and environmental compliance on every project.”

Gerry Carolan Operations Director, Civil Engineering, Stockton Group

Extensive drainage

Stockton installed a comprehensive internal and external drainage network to manage foul water and stormwater. This included embedding stainless-steel linear channels to continuously catch water. These were chosen for their corrosion-resistant and durable qualities – important for the hygienic environment food processing requires.

Stockton also installed gullies to collect water run-off before it accumulates and prevent sewer gases escaping into the open air or inside the building. The team constructed manhole chambers to allow safe access to the pipe network for maintenance engineers to complete routine inspections and built a pumping station to lift collected water upward and on toward the nearest sewer line.

Extensive drainage

Structural and external works

Stockton constructed new Reinforced Concrete (RC) slab to extend the existing factory footprint, and re-levelled the warehouse floor. The team built large pad foundations as the load-bearing supports for new steel columns as part of the extended building’s structural framework and installed chiller plinths installed to isolate vibrating cooling equipment from the main building structure. Advanced Damp Proof Membranes (DPM) were installed too to protect stored goods.

Outside, Stockton constructed footpaths with kerbs and path edgings, finished with a tarmacadam topping for a smooth, durable, weather-resistant finish for workforce and pedestrian access.

Structural and external works

Health, safety and environmental compliance

Stockton Group achieved full compliance with all health and safety requirements, and received a score of 100% from an external Achilles Audit visit to site. 

Health, safety and environmental compliance