Subsea landfalls completed for one of the UK’s largest tidal energy schemes

Author
Fiona o’Connell, Managing Director
6 May 2026

The Morlais project, delivered by Menter Môn, is a pioneering tidal stream initiative off the coast of Holy Island, Anglesey, designed to generate low-carbon electricity while supporting local communities and economic growth. Spanning a 35 km² seabed area, the site has the potential to produce up to 240 megawatts of renewable energy, positioning Anglesey (Ynys Môn) as a key player in the UK’s energy transition.

A critical subsea infrastructure was required to connect offshore tidal devices to the onshore grid, which presented a complex landfall challenge in a sensitive coastal environment. Conventional trenching methods were not viable due to environmental constraints, coastal conditions, and the need to minimise disruption. A fully trenchless approach was required.

Stockton Group was engaged by Menter Môn to deliver 5 x 550m Horizontal Directional Drilling (HDD) landfalls and, as Principal Contractor, to take full responsibility for planning, managing, monitoring, and coordinating the entire construction phase.

Decor Subsea landfalls completed for one of the UK’s largest tidal energy schemes
Horizontal Directional Drilling installation for subsea infrastructure

Horizontal Directional Drilling installation for subsea infrastructure

Stockton Group has successfully completed five long-distance Horizontal Directional Drilling (HDD) installations, each extending approximately 550 metres from a single onshore entry point and exiting subsea.

This approach allowed offshore offshore tidal systems to be connected to the onshore grid network without disturbing the coastline or surrounding environment.

Each bore was reamed to approximately 508mm diameter and fitted with HDPE ducts, creating a continuous conduit for subsea power cables.

Project Summary

5 HDD landfalls delivered from a single entry location
550m bore length per installation
Principal Contractor under CDM 2015 regulations
Full construction phase management, coordination, and compliance
Installation of HDPE ducts for subsea cable infrastructure
Supporting a project with up to 240MW renewable energy capacity

Project Breakdown

Trenchless landfall solution

Enabling subsea cable installation without coastal disruption

Single entry point strategy

Reducing surface impact and simplifying site logistics

Renewable energy infrastructure

Supporting one of the UK's most ambitious tidal energy schemes

Quote Author

“Stockton continually demonstrated great care and consideration whilst working within environmentally sensitive areas. I can confidently recommend them as a potential Design and Build Contractor for Horizontal Directional Drilling works.”

Ian Johnson Senior Project Manager, E.ON Climate & Renewables

ENVIRONMENTAL CHALLENGES

As with many coastal projects, environmental sensitivity played a central role in the project’s planning and execution.

The site supports protected wildlife, including chough bird populations. This meant that construction activity was restricted to winter working windows (October–March) to minimise ecological impact, with Stockton strictly adhering to environmental consents and regulations

Ground conditions added further complexity. presented significant technical challenges. Geological mapping identified hard rock formations consisting of psammite and pelite materials that demanded precision drilling and robust equipment capable of maintaining accuracy over long distances.

ENVIRONMENTAL CHALLENGES

DESIGN & COORDINATION

Operating as Principal Contractor, Stockton took full responsibility for planning, managing, monitoring, and coordinating the entire construction phase through to delivery and compliance

Working closely with design partner Waterman Infrastructure and Environment, detailed bore profiles and alignments were developed to ensure compliance with all consented parameters while maintaining drilling efficiency.

Each stage of construction was governed by a bespoke inspection and test plan, ensuring consistent quality and adherence to internal management systems.

Following completion of each bore, HDPE ducts of approximately 560m were installed to act as conduits for subsea power cables, creating a seamless connection between offshore generation and the National Grid.

Despite the challenges posed by restricted working windows, complex geology and strict environmental controls, the project was delivered safely, efficiently, and to the highest standard.

By combining technical expertise with innovative thinking, the Stockton team continues to support the growth of renewable energy infrastructure across the UK and beyond.

DESIGN & COORDINATION