Overcoming Flood Risks To Deliver a Trenchless Crossing at Westmoor Resevoir

Author
Gearoid O’Connell, Director
10 September 2025

The Westmoor Reservoir project covers the delivery of reservoir improvement works near Langport, Somerset, which was completed in November 2025. Work was undertaken to ensure the safe and continued operation of the reservoir, keeping the wider water level management system efficient and guaranteeing protection of local communities and downstream towns.

STOCKTON GROUP was brought in help with flood storage in the West Moor and South Moor reservoirs, collectively known as Westmoor. As part of the project, Stockton delivered a 220m trenchless river crossing, using Direct Pipe®, to form a 1400mm I.D. siphon below the River Parrett, to replace the Midelney Siphon.

Decor Overcoming Flood Risks To Deliver a Trenchless Crossing at Westmoor Resevoir
Direct Pipe® installation

Direct Pipe® installation

Stockton completed the trenchless installation of a 220m trenchless river crossing by utilising Herrenknecht’s Direct Pipe® system.

Direct Pipe® (a hybrid micro-tunnelling and pipe-jack system that lines the tunnel as it advances) was selected to avoid surface level disruption when crossing the River Isle.

Project Summary

220m trenchless river crossing utilising Direct Pipe®
Difficult ground conditions and logistical implications due to flood plain location
Technical difficulties with a limited construction window and site access
Installation of sheet-piled cofferdam

Project Breakdown

1400m I.D siphon

This siphon was formed below the River Parrett, to replace the Midelney Siphon

SSSI

The project location is a Site of Special Scientific Interest (SSSI), introducing environmental constraints

Flood Plain

The site location sits within an existing flood plain that floods annually over the winter months, preventing access to site

Quote Author

This project, required us to navigate multiple logistical and technical obstacles, including difficult ground conditions, a flood plain location, and a short construction window. As always, the team worked through the challenges, efficiently managing and overcoming each risk to safely deliver a Direct Pipe© solution. 

Stuart Stephens Director of Special Projects

CHALLENGING CONDITIONS

A cofferdam was installed as a crucial preparatory step before using Direct Pipe©, creating a watertight enclosure to offer a stable foundation for the equipment, and provide a safe area for pipe assembly. The ground was excavated using a long-reach excavator, and a 1.35m deep concrete base was added. 

The project location is a Site of Special Scientific Interest (SSSI), introducing environmental constraints that meant the pipe stringing platform and mud recycling compound was significantly restricted in size, to protect local wildlife and nature reserves. 

Unforeseen changes in geology delivered a range of engineering and commercial challenges, with significantly harder ground conditions than expected and high volumes of water putting the Stockton team under pressure to maintain progress. 

The site location sits within an existing flood plain that floods annually over the winter months, preventing access to site, squeezing the construction programme into the accessible months of the year. 

CHALLENGING CONDITIONS

HANDS-ON PROJECT MANAGEMENT

Due to the critical nature of the crossing, Stockton participated in regular planning reviews with the client and subcontractors. Stockton established a safety-first culture on site by enforcing thorough site inductions and regular toolbox talks for all personnel. 

This full project management capability means Stockton is able to manage complex, high-risk projects and deliver them to industry leading quality and standards, in a safe and practical manner, becoming a contractor of choice across the sector. 

Throughout the project, Stockton continually worked with the Environment Agency to to ensure safety and environmental compliance.  

HANDS-ON PROJECT MANAGEMENT