SANDY WAY, TAMWORTH
CIVILS WORKS PACKAGE
G F TOMLINSON

“I just wanted to say thanks for all your hard work in completing the pad foundation in record time. We very much appreciate the hard work and hours you have put in – the team is a credit to your company.”

TONY WARNER
SENIOR SITE MANAGER
G F TOMLINSON

THE PROJECT
In an exciting new partnership with G F Tomlinson, Stockton has commenced works on-site with plans to construct four new warehouses opening in summer 2022. This is a multi-disciplined project that requires our Civils team to undertake a variety of responsibilities such as:

  • Project management
  • Full site setting-out and control
  • HV service diversion works
  • Drainage & Section 278 Highway Works
  • Large mass-fill foundations
  • Kerbing and external works.

SAFETY
All Stockton sites are Covid compliant and the team continue to practise strict Covid-19 procedures. A weekly team-meeting is undertaken to catch up with recent project activities, discuss any health & safety concerns and report any recent accidents/incidents/near-misses as a means of preventing and reducing future issues. An external HSEQ auditor visits our sites to ensure full H&S procedure compliance. 

SCOPE OF WORK
Principle activities include:

  • Project management
  • Site preparation and survey
  • Bulk excavations
  • Below-ground foul, SuDS drainage and petrol interceptor 
  • RC substructure works
  • External works including kerbing, linear drainage channels, preparation of car parks and footpaths
  • Section 278 Highway Works.

PROJECT SUMMARY

  • A range of Civils covering substructures, below-ground drainage and petrol interceptors, large mass-fill foundations, kerbing and preparations for new car parks including Section 278 Highway Works
  • Environmental; dust control zones, spill kits and drip trays, dedicated concrete washout zones
  • G F Tomlinson have consistently scored Stockton as “very good” in surveys and are pleased to add us to their supply chain
  • Due to be completed summer 2022