
BACTON GAS PLANT
900MM STEEL PIPELINE
AMEC SHELL
“The project was delivered safely and to a high quality, and I have no hesitation in recommending Stockton Drilling for future drilling projects.”
FONS CLAESSEN
PLANT INSTALLATION MANAGER
SHELL BACTON
THE PROJECT
The project consisted of a 600m horizontal directional drill (HDD) to install a 914.4mm steel pipeline; the first section of line for the Shell UK Bacton natural gas plant in Norfolk. Working for main contractor AMEC, Stockton provided specialist drilling services and managed the drilling site and HDD works. In addition to the HDD it was necessary to construct a cofferdam at the site heli-pad to enable safe access.
HDD
Horizontal Directional Drilling enabled Stockton to create a secure route without disturbing the plant and equipment within the Shell compound. A pre-welded and tested pipeline string was then pulled through the prepared hole completing the installation with no risk of subsidence or post construction settlement.
SAFETY
As this was an operational gas site all personnel required OFGES approval and were trained in the relevant Shell H&S policies for the Bacton site. Stockton often works within a third-party site, and as part of the project planning process will complete a thorough safety and environmental assessment. In particular Stockton will develop a site-specific health and safety plan which will fully integrate the host organisation’s procedures and ensure that site induction and working methods fully meet the host and client requirements.
PROJECT MANAGEMENT
Stockton worked closely with AMEC and Shell, with involvement in the up-front project design and how to make best use of the specialist HDD techniques. One key element of the project was to minimise the impact on the local environment. By adopting strict traffic management and environmental controls the local environment and community remained undisturbed throughout the entire drilling process.